Rajasthan Launches Tender for Large-Scale 1 GWh Battery Storage Project
Rajasthan has issued a global tender for the development of a large-scale 1,000 MWh Battery Energy Storage System (BESS). This project, one of the state's largest planned procurements, aims to enhance grid stability and support renewable energy integration. Bids for this build-own-operate project are due by December 21, 2026. The project is eligible for central financial assistance under a viability gap funding scheme.
Rajasthan Rajya Vidyut Utpadan Nigam Limited (RRVUNL) has issued a global tender for the development of a large-scale Battery Energy Storage System (BESS) with a capacity of 250 MW and 1,000 MWh. This project, designed for a four-hour duration, is set to become one of the largest planned grid-scale storage procurements in the Indian state of Rajasthan.
The project will be developed under a build-own-operate (BOO) model and is eligible for central financial assistance through a viability gap funding (VGF) scheme. The selected developer will be responsible for establishing and operating the storage facility, making it available to RRVUNL for charging and discharging electricity as required. The system will draw power from Rajasthan Rajya Vidyut Prasaran Nigam Limited (RVPN) or local distribution companies and inject stored electricity into their networks based on dispatch instructions from the state load despatch centre.
Among the technical requirements outlined in the tender is the mandatory inclusion of a power conversion system that is 100 percent grid-forming and inverter-based. It is required that all inverter blocks function in grid-forming mode, adhering to relevant technical standards and regulatory stipulations. Bids must be at least 200 MWh in size, and any incremental additions to a bid must be a minimum of 50 MW.
The full project capacity is scheduled for commissioning within 18 months of the effective date of the battery energy storage purchase agreement. The VGF funding will be released in three stages: 20 percent upon financial closure, 50 percent after achieving commercial operation, and the remaining 30 percent after the first year of operations. Developers seeking VGF support must ensure that at least 20 percent of the total project cost is met through local content, including indigenously developed energy management system application software.
The deadline for online bid submissions is December 21, 2026. Interested parties are required to submit a document fee of 500,000 Indian rupees and a bid processing fee of 2,500 rupees plus GST. Additionally, a performance bank guarantee of 800,000 rupees per MWh and an earnest money deposit of 320,000 rupees per MWh are required. This news was sourced from Bing News.
Want to know what this means for you?
Talk to Oranje-Eco →This article is an Oranje-Eco summary of a report by Bing News: "BESS" tender. Read the original: Bing News: "BESS" tender.
What impact do you anticipate such large-scale storage projects will have on the energy transition in emerging markets?
No comments yet - be the first.