Sonnedix Activates 125 MWh Co-located Battery Storage Project in Japan
Sonnedix has commenced commercial operations of its first battery energy storage system (BESS) in Japan. The 125 MWh project in Oita prefecture is co-located with an existing 39 MW solar PV plant. This system enables time-shifting of solar output and response to grid demand, contributing to a more stable power system.
Global renewable energy producer Sonnedix has initiated commercial operations for a 125 MWh co-located battery energy storage system (BESS) in Japan's Oita prefecture. This marks the company's inaugural storage asset in the country.
The facility is situated alongside an operational 39 MW solar PV plant in Kyushu. This co-location strategy allows the developer to shift solar generation to more opportune times and dispatch power in response to grid requirements, thereby reducing the need to curtail excess generation. Historically, Kyushu has experienced some of Japan's highest solar curtailment rates, primarily due to grid infrastructure limitations.
Construction of the Oita project began in October 2025, reaching commercial operation in approximately 13 months. Toshiba Energy Systems & Solutions Corporation served as the engineering, procurement, and construction (EPC) contractor, deploying Tesla Megapack units. The cabinet configuration observed suggests the use of Tesla Megapack 2XL.
Japanese utility major Osaka Gas is responsible for the asset's trading and market interactions. To support its development, Sonnedix secured a JPY 21.4 billion ($139 million) non-recourse refinancing facility, arranged by MUFG Bank.
The commissioning of the Oita project is part of Sonnedix’s broader initiative to retrofit storage solutions across its 570 MW Japanese solar portfolio and its wider global fleet. Tomomichi Kageyama, the managing director of Sonnedix Japan, explained that incorporating storage into their operational solar plant allows them to adjust power generation to periods of higher demand and react more efficiently to market dynamics, thereby contributing to a more robust and dependable power infrastructure.
This project contributes to a rapidly expanding trend of utility-scale battery deployments throughout Japan, following recent grid connections and portfolio launches by other entities such as Sunpin Japan and Orix.
This article is based on information from ESS News.
Want to know what this means for you?
Talk to Oranje-Eco →This article is an Oranje-Eco summary of a report by ESS News. Read the original: ESS News.
How do you anticipate such co-located storage projects will impact grid stability in regions with high renewable energy penetration?
No comments yet - be the first.